How Is a CNC Machining Quotation Calculated? Una guida passo-passo

Telecomunicazioni MACCHININE CNC

If you’re sourcing CNC-machined parts for your project, understanding how quotations are calculated is key to avoiding overpaying or misinterpreting costs. A CNC machining quotation isn’t a random number—it’s a detailed sum of tangible factors like material use, Tempo di lavorazione, e lavoro. This guide breaks down the calculation process, core influencing factors, and practical examples to help you verify and optimize quotes.

1. 8 Core Factors That Shape a CNC Machining Quotation

Every line item in a CNC quotation ties back to specific cost drivers. Di seguito è riportato una rottura dettagliata di ciascun fattore, with real numbers to illustrate how they impact the final price:

(1) Costo materiale

Material cost forms the base of the quotation and is calculated by the part’s weight or volume. Different materials have vastly different unit prices, directly affecting this component:

Tipo di materialeUnit Price (RMB/kg)Calculation Example (0.5kg Part)Casi d'uso chiave
Acciaio al carbonio30 ~ 8015 ~ 40 RMBStaffe strutturali, parti a basso carico
Lega di alluminio50 ~ 10025 ~ 50 RMBComponenti automobilistici, electronic cases
Acciaio inossidabile100 ~ 20050 ~ 100 RMBStrumenti medici, food-processing parts
Rame100 ~ 20050 ~ 100 RMBConnettori elettrici, dissipatori di calore

Nota: Scrap material (typically 10–20% of the raw material weight) is often included in the quotation to account for cutting waste.

(2) Machining Time Cost

Machining time is the single largest variable in most quotations, as it combines equipment and labor charges. It includes three key phases:

  • Tempo di programmazione: 0.5–2 hours for simple parts (PER ESEMPIO., a flat block) and 3–8 hours for complex parts (PER ESEMPIO., parts with 3D curved surfaces). Programmers typically charge 80–150 RMB/hour.
  • Actual Machining Time: Depends on cutting speed, tool path, and part size. A small aluminum part (5cm × 5cm) may take 1–2 hours, while a large stainless steel part (20cm × 20cm) could take 4–8 hours.
  • Serraggio & Tool Change Time: 0.2–1 hour per part. Multi-sided machining (PER ESEMPIO., 4-axis work) can double this time, adding 0.4–2 hours to the total.

Equipment hourly rates vary by type:

  • Ordinary 3-axis CNC machines: 50–100 RMB/hour
  • High-end 5-axis CNC machines: 150–300 RMB/hour

(3) Equipment Depreciation

CNC machines cost tens of thousands to millions of RMB, so depreciation is spread over their 5–10-year lifespan and included in the quotation. Per esempio, UN 500,000 RMB 3-axis machine has an annual depreciation of 50,000–100,000 RMB, which translates to 20–40 RMB/hour added to the equipment cost.

(4) Manutenzione & Abbigliamento per utensili

Utensili (PER ESEMPIO., mulini finali, esercitazioni) wear out after repeated use and need replacement. A standard carbide end mill costs 50–200 RMB and lasts for 20–50 hours of machining—adding 1–10 RMB/hour to the quotation. Other maintenance costs (lubricating oil, filter changes) add an extra 5–15 RMB/hour.

(5) Labor Cost

Labor covers operators, quality inspectors, and sometimes programmers. Hourly rates vary by region and skill:

  • Entry-level operators: 50–80 RMB/hour
  • Skilled operators (for 5-axis machines): 100–150 RMB/hour
  • Quality inspectors: 80–120 RMB/hour

For a part that takes 3 ore di macchina, labor cost typically ranges from 150–450 RMB.

(6) Costo post-elaborazione

Most parts require post-processing to meet functional or aesthetic standards, and each step adds to the quotation:

Post-Processing TypeGamma di costi (RMB/part)Scopo
Anodizzante (Alluminio)50 ~ 150Resistenza alla corrosione, personalizzazione del colore
Elettroplazione80 ~ 200Resistenza all'usura, conducibilità elettrica
Trattamento termico100 ~ 500Indurimento (PER ESEMPIO., quenching steel parts)
Tapping/Drilling30 ~ 80Adding threaded holes for assembly

(7) In parte complessità & Precisione

Complexity and precision directly increase machining time and skill requirements, pushing quotes higher:

  • Parti semplici (block shapes, tolerances ±0.1mm): Lower time and skill needs—quotes are 50–150 RMB/part.
  • Parti complesse (pareti sottili <2mm, tolleranze ± 0,01 mm): Require slower cutting speeds and more programming—quotes jump to 200–1,000 RMB/part.

Esempio: A stainless steel part with ±0.01mm tolerance costs 3x more than the same part with ±0.1mm tolerance.

(8) Volume dell'ordine

Batch size unlocks volume discounts, as fixed costs (programmazione, impostare) sono distribuiti in più parti. Here’s how volume affects unit quotes for a simple aluminum part:

Volume dell'ordineUnit Quotation (RMB/part)Discount vs. 1–10 PiecesRagionamento
1–10 pezzi1000%High fixed cost per unit
11–50 pezzi8020%Fixed costs spread across more units
51–100 pezzi7030%Lower per-unit material and labor costs
100+ pezzi6040%Bulk material discounts + optimized setup

2. 3 Common Methods to Calculate CNC Machining Quotations

Suppliers use different formulas to compile quotes, depending on part type and order size. Di seguito sono riportati i metodi più comuni, with step-by-step examples:

Metodo 1: Time-Based Quotation (Most Common for Complex Parts)

This method focuses on total machining time, combining equipment, lavoro, and other time-related costs.

Formula: Total Quotation = (Equipment Hourly Rate + Labor Hourly Rate) × Total Machining Time + Costo materiale + Costo post-elaborazione

Esempio:

  • Equipment hourly rate: 100 RMB (3-Asse CNC)
  • Labor hourly rate: 60 RMB (operator + inspector)
  • Total machining time: 4 ore (1 hour programming + 2.5 hours machining + 0.5 hours clamping)
  • Costo materiale: 40 RMB (0.5kg aluminum alloy × 80 RMB/kg)
  • Post-processing cost: 80 RMB (Anodizzante)

Total Quotation = (100 + 60) × 4 + 40 + 80 = 160 × 4 + 120 = 640 + 120 = 760 RMB

Metodo 2: Material-Based Quotation (Common for Simple Parts)

This method starts with material cost and adds a fixed or variable machining fee.

Formula: Total Quotation = (Material Unit Price × Part Weight) + Machining Fee + Costo post-elaborazione

Esempio:

  • Material unit price: 50 RMB/kg (acciaio al carbonio)
  • Peso parziale: 1kg → Material cost: 50 × 1 = 50 RMB
  • Machining fee: 200 RMB (includes equipment, lavoro, and depreciation for a simple block part)
  • Post-processing cost: 50 RMB (perforazione 2 buchi)

Total Quotation = 50 + 200 + 50 = 300 RMB

Metodo 3: Fixed Quotation (For Standardized Parts)

For simple, parti ripetibili (PER ESEMPIO., distanziatori, standard fasteners), suppliers often offer a fixed quote that includes all costs. Per esempio:

  • A standard aluminum spacer (10mm × 5mm) may have a fixed quote of 20–30 RMB/piece for orders of 100+.
  • A stainless steel bolt (M10 × 20mm) could have a fixed quote of 15–25 RMB/piece.

3. How to Verify and Optimize a CNC Machining Quotation

Once you receive a quote, you can cross-check its 合理性 (reasonableness) and reduce costs with these steps:

  1. Break down the quote: Ask the supplier to itemize costs (materiale, Tempo di lavorazione, post-elaborazione) to identify overcharges. Per esempio, if the material cost for a 0.5kg aluminum part is listed as 80 RMB (well above the 25–50 RMB market range), clarify the reason.
  2. Ottimizza la progettazione delle parti: Semplifica la geometria (PER ESEMPIO., replace curved surfaces with straight lines) to cut machining time by 10–30%. Add hollow structures to reduce material weight by 15–25%.
  3. Negotiate volume discounts: Even if you need 20 parti ora, ask for a “future batch” discount (PER ESEMPIO., 15% off if you order 50+ entro 6 mesi).
  4. Adjust precision requirements: Use ±0.05mm tolerance instead of ±0.01mm if the part doesn’t need ultra-high precision—this can lower machining time by 20–40%.
  5. Choose cost-effective post-processing: Salta i passaggi non necessari (PER ESEMPIO., polishing internal surfaces that won’t be seen) to save 50–150 RMB/part.

Yigu Technology’s Perspective on CNC Machining Quotations

Alla tecnologia Yigu, Crediamo transparency is the foundation of trust in CNC machining quotations. Many clients struggle with “black-box” quotes that lack itemized costs, leading to confusion. We always break down quotes into material, Tempo di lavorazione, lavoro, and post-processing costs, so clients understand exactly where their money goes. We also proactively suggest optimizations: Per esempio, if a client requests a stainless steel part with ±0.01mm tolerance for a low-load application, we’ll recommend aluminum alloy with ±0.05mm tolerance—cutting the quote by 30–50% without sacrificing performance. Inoltre, we offer flexible volume discounts, Anche per piccoli lotti, by aggregating orders from multiple clients. Our goal is to help clients get fair, cost-effective quotes that align with their actual needs.

Domande frequenti

  1. Why is scrap material included in the material cost of a CNC quotation?

Scrap material (10–20% of the raw material weight) is included because CNC machining produces waste (PER ESEMPIO., talee, leftover raw material after shaping). Suppliers factor this in to cover the full cost of the raw material they purchase, even if not all of it ends up in the final part.

  1. Can I negotiate the machining time cost in a CNC quotation?

Yes—if you can show that the machining time is overestimated. Per esempio, if the quote lists 5 hours for a simple aluminum block (which typically takes 1–2 hours), provide a 3D model or drawing to prove the part’s simplicity. Suppliers may adjust the time to 2–3 hours, lowering the total quote by 40–60%.

  1. What’s the difference between a “time-based” and “material-based” quotation?

A time-based quotation focuses on total machining time (combining equipment and labor) and is better for complex parts with variable machining needs. A material-based quotation starts with material cost and adds a fixed machining fee, making it simpler for basic parts (PER ESEMPIO., blocchi, distanziatori) where machining time is predictable. Choose the method that matches your part’s complexity for the most accurate quote.